Objective of the project

The overall objective of the Nuijamaa Phase II project was to strengthen the local and regional sustainable economic development by expanding the existing border crossing facilities to increase border crossing throughput from Russia to Finland.

Main activities

- To carry out the final designs/plans for the needed infrastructure work; - To carry out necessary tendering procedures and; - To carry out the construction of transport area works.

Achievements

The objective was reached by the following activities: 1) to carry out final designs/plans for the needed infrastructure work, 2) to carry put necessary tendering procedures, and 3) to carry out the construction of transport area works. The transport infrastructure works consisted of construction of new area for traffic arriving to Finland, construction of new lanes near the main building, and border crossing management planning and implementation. The new lane checking area and new checking procedures have increased the border crossing capacity. According to the Finnish Border Guard statistics, the new checking procedure is 50% faster, and the yearly capacity is 6,6 million people versus earlier 2,6 million.



Basic information


Acronym

Nuijamaa Border Crossing Development Phase II

Duration

2013-02-01 - 2014-12-31

Total Budget / Programme funding

1 130 000 € / 904 000 €


Lead partner

The Finnish Transport Agency
Lead partner web-site

Partners

The Centre for Economic Development, Transport and the Environment of South-East Finland
The Finnish Customs
The Finnish Border Guard
City of Lappeenranta
The Road Committee of the Leningrad Region