Kt 89 Preparation of the Paltamo-Vartius road plan between Jokimäki and Heinilä
Funded by Interreg II Karelia 1996-1999

Objective of the project

The objective of the project was to draw up an 86.3 km road plan between Jokimäki-Heinilä. The plan was going to consist of several parts, beginning from the Jokimäki-Revonkanta section, followed by the Revonkanta-Arola and Arola-Heinilä sections. Plans for all three sections of the road will be completed by 1999. The plan was going to be drawn up taking into account the quality requirements for class II main roads.

Main activities

Achievements



Basic information


Acronym

Duration

1997-01-01 - 1999-12-31

Total Budget / Programme funding

689 542 € / 336 362 €


Lead partner

Oulu road district
Lead partner web-site

Partners